Lockheed Martin Vacuum Chamber Relocation
Client: Lockheed Martin Missiles & Space Co,
Project: Relocation of a Thermal Vacuum Chamber at the Sunnyvale Campus.
Project Cost: $1,300,000
Project Description:
- Design and installation of a new state of the art control system to operate the chamber.
- A data collection system to collect information during testing.
- A vacuum pumping system.
- A LN2/GN2 process system required to operate the chamber.
Scope of Work:
- Equipment Relocation Planning.
- Disconnect existing control and process systems associated with the chamber.
- Design and construct 20,000 square feet of space in an
existing building to house the chamber. The new space includes a 1500sf 10k clean room, a testing area, a control room, and office spaces.
|